The Bunnings Workshop community can help with your home improvement projects.

The Father & Son Bar - man cave construction project

Steps

12

Step 1

1/2
DAY 1 & 2 - ***THE FATHER & SON BAR***

Alex and I kicked off the project last weekend. We started off by giving the slab a good pressure wash on the Friday arvo’. The following morning, we applied a Moisture barrier to the concrete.

We plan to build a false floor over the slab and so a painted or sealed finish wasn't required. We came across a product called “Moisture Proof” (Manufactured by Duracore). By using this product, we avoided the messy and time-consuming process of traditional two part epoxy systems. It also turned out to be very cost effective. The other big benefit being that it is a trafficable surface.

No mixing was required, and a single coat was all that was needed. The product was applied using a low pressure weed sprayer. After 45 minutes, any excess pooling was pushed around with broom. The product is fully dry within 24 hours. The product is designed to penetrate the concrete up to 200mm and forms a non-destructive, 100% colloidal gel. The colloidal gel provides a permanent barrier that withstands hydro static pressure (rising damp); which is all we needed it to do.

Next, we moved onto some painting. Due to the way that we intend to line the walls, part of the frame will remain visible. We started off using a palm sander together with hand sanding. Very quickly realising the job would be much quicker by using a wire wheel on a drill.

The masking wasn’t necessarily required as the adjacent surfaces will be covered. It was mostly about showing Alex the entire painting process. As you can see from the end result, I gave up on the masking by the time the top coat went on 😅.

The frame at the rear will most likely end up being covered. I figured we were already there, and it gives us some flexibility if we change direction later on.

After hitting it all with the sander / wire wheel, it was given a wipe down with solvent. We then applied two coats of primer followed by two coats of topcoat (Colorbond ‘Monument’). The $149 investment in a spray gun was well worth the investment.
 
IMG_1536.JPGIMG_1905.JPGIMG_1913.JPGIMG_1943.JPGIMG_1952.JPGIMG_E2033.JPGIMG_1908.JPGIMG_1951.JPG
Next Step

Step 2

2/2
***THE FATHER & SON BAR***

Step 2: “Rough In”
After consulting with an Electrician, we made the decision to save ourselves some cash and do the Electrical “Rough In” ourselves.

Before the shed slab was laid, conduit was trenched in with a 20amp supply cable. We’ve just finished installing 3 circuits in the shed. Each circuit has been installed in conduit and affixed to the inside of the wall girts and roof purlins.

-Circuit 1-
2.5mm Twin and Earth cable. Allocation has been made for 12 x Double GPO’s (2 in each bay). These will run on a 20 Amp RCBO. To ensure no cable ever touches the steel structure, we have used “Purlmate” 3650 mounting blocks at the intended fit off point. The conduit was reduced down to 20mm corrugated flex conduit at the mounting blocks to give the cable protection in the void that will be behind the wall lining and steel frame.

-Circuit 2-
Another run of 2.5mm Twin & Earth installed in conduit in the upper girt. This will power the 3.5kw Split System Aircon that will end up on the back wall. As such, it requires its own circuit. This will come back to the distribution board on a 16 Amp RCBO.

-Circuit 3-
1.5mm Twin & Earth cable installed in conduit inside the roof purlins. This circuit will power the lighting and will come back to the distribution board on a 10 Amp Distribution board. The flex conduit pictured will eventually tuck into the ceiling battens that we intend to use to mount the lining boards to.
 
A recessed surface mount Distribution Board will house the RCBO’s together with a 32amp MCB Circuit Breaker.
Once the walls have been completed, we will engage an Electrician to complete the fit off and connect the supply cable to the house.

School holidays kick in this week. I’ve got a couple more days of work until I go into 3 weeks of leave. Then we can get properly stuck in.

Top Tip: I've since learned that the correct conduit for this install would of been Medium Duty (MD) - They grey stuff. HD is usually only used for underground applications. It is not UV stable. If exposed to sunlight, it will become brittle and crack if impacted. Luckily for me, the conduit will be covered and so it won't be an issue. If the HD was going to be exposed to sunlight, it would need to be painted.

Materials

Tools
Haron 42mm Pipe / Tube Cutter

 


JacobZ_0-1734068057594.jpeg

 

JacobZ_1-1734068057638.jpeg

 

JacobZ_2-1734068057647.jpeg

 

JacobZ_3-1734068057835.jpeg

 

JacobZ_4-1734068057711.jpeg

 

JacobZ_5-1734068057759.jpeg

 

Previous Step
ruredi13
Cultivating a Following

Re: The Father & Son Bar - man cave construction project

**New Post**

”Rough In” has been added to Step 2. 

Dave-1
Community Megastar

Re: The Father & Son Bar - man cave construction project

Evening @ruredi13 

You guys are powering along.... and non intentional pun :smile: But ill take it :smile:

Nice tidy work btw.

 

Dave

Why join the Bunnings Workshop community?

Workshop is a friendly place to learn, get ideas and find inspiration for your home improvement projects